How to get a soil validation report

Updated

What a soil validation report is

You get a soil validation report by having a competent environmental consultant check and record the clean-up of a contaminated site, then submitting their report to the council to discharge the planning condition. Official guidance calls it a verification report; councils and consultants often say validation report or Phase 4 report. They mean the same thing.

It is the last step in Land Contamination Risk Management (LCRM), the Environment Agency’s guidance. The report shows the remediation was done as agreed and the risk has been brought down to the agreed level.

Where it fits in the process

LCRM has three stages:

  1. Risk assessment: desk study, site walkover and, where needed, ground investigation.
  2. Options appraisal: choosing how to deal with the contamination.
  3. Remediation and verification: doing the work and proving it worked.

Many councils still use the older phase names: Phase 1 desk study, Phase 2 site investigation, Phase 3 remediation strategy, Phase 4 verification. Plymouth and Portsmouth both describe it this way.

The validation report is planned before any digging starts. The remediation strategy includes a verification plan, which sets out what will be sampled, how often, which tests, the pass criteria and who is responsible. Portsmouth says the council must approve the remediation strategy before work starts. If nobody agreed a verification plan, there is often nothing to validate against.

Who writes it

LCRM says stage 3 needs a competent person with training, knowledge and experience in remediation. In practice that is an environmental or geotechnical consultant. Plymouth strongly advises using an appropriately qualified consultant and notes it cannot recommend one.

The National Quality Mark Scheme (NQMS), run by CL:AIRE, lets a suitably qualified person sign off a land contamination report. It is voluntary, and the regulator still reviews the report. GOV.UK says the NQMS does not currently apply in Northern Ireland.

Responsibility for a safe development stays with the developer or landowner, not the council, according to the government’s planning guidance for England.

What goes in the report

LCRM lists what a verification report should cover:

  • background and basic site details
  • what remediation was done, and the conceptual site model (the picture of source, pathway and receptor)
  • how verification was carried out, including volumes of material treated and imported
  • waste records, and gas protection measures if fitted
  • chemical and physical test results, with plans, photos and sampling locations
  • the final site condition, any ongoing management, and an updated conceptual site model

If long-term monitoring was part of the plan (ground gas or groundwater, for example), a separate monitoring report follows once the criteria are met.

What groundworkers and muck away firms need to keep

Much of the evidence in a validation report comes from the people moving the soil. If the records are missing, the consultant cannot verify the work and the condition stays open.

  • Soil taken off site. Plymouth expects waste transfer notes as part of the Phase 4 evidence. In England and Wales, every business transfer of non-hazardous waste needs a waste transfer note under the duty of care, with the List of Waste code, quantity, the transferor’s SIC code, and the names and addresses of both parties; both keep it for at least two years. Hazardous soil moves on a hazardous waste consignment note instead. Contaminated soil must go to a permitted site that accepts that class of waste. See where to tip contaminated soil and hazardous waste disposal.
  • Soil brought in. Imported topsoil and fill for a clean cover layer is usually sampled and tested, and Plymouth lists sampling of imported material with certificates as a minimum. Ask your supplier for test certificates and keep delivery records. Council rules on testing rates vary, so check the condition wording.
  • Soil reused on site. If excavated soil is waste, reusing it needs an environmental permit or a registered exemption. In England and Wales, the voluntary CL:AIRE Definition of Waste Code of Practice is a way to show some excavated soil is not waste when reused on its site of origin or moved between sites. It needs a Materials Management Plan and a Qualified Person declaration submitted before the soil is reused or moved. Check with the Environment Agency or Natural Resources Wales if unsure. Depositing waste soil on land without a permit or registered exemption is a criminal offence.

Photos, site diaries and dig-out plans with depths help too.

Getting the condition discharged

Send the report to the council planning department with an application to discharge the condition. The council’s environmental health or contaminated land officer will review it. Plymouth calls the Phase 4 report essential to discharge the condition, and says it also lets the council confirm the remediation in future property searches.

Check the exact wording of your condition. Some say the report must be approved before the building is occupied.

Rules in each nation

  • England: LCRM and the government’s planning practice guidance on land affected by contamination. Councils set their own conditions.
  • Wales: GOV.UK says Natural Resources Wales expects LCRM to be followed, along with NRW’s own land contamination guidance. Many Welsh councils publish a shared developers guide; check your council’s contaminated land page.
  • Scotland: SEPA also expects LCRM to be followed, but the legal definition of contaminated land differs from England. Check with SEPA and your council.
  • Northern Ireland: Part 2A of the Environmental Protection Act 1990 does not apply. GOV.UK points to the DAERA practice guide on redeveloping land affected by contamination. Check with DAERA and your council.

Finding a site for the soil

To find a permitted site for soil leaving the job, search by postcode on Tip Directory or browse landfill sites and waste transfer stations. For background on the clean-up itself, see what soil remediation is and when it is required.

Sources

Find a tip near you by postcode

Report a problem

Page:

What is wrong?

We only use your email to reply about this report. See our privacy page.