How to write a site waste management plan (SWMP)

Updated

To write a site waste management plan (SWMP), list every type of waste the job will produce, estimate how much of each, decide where each load will go, and record what actually leaves site. No UK nation has a general law requiring a SWMP today, but the waste duties the plan helps you meet are all legally binding.

When you need a site waste management plan

England: SWMPs were compulsory for construction projects over £300,000 from 6 April 2008. That law was revoked on 1 December 2013.

Scotland and Northern Ireland: NetRegs, the guidance service from the Scottish and Northern Irish regulators, says you do not need a SWMP for a construction project.

Wales: The Waste (Wales) Measure 2010 lets Welsh Ministers make SWMP regulations. We found no such regulations in force, but check with Natural Resources Wales if your job depends on it.

A client’s contract or a planning condition can still require a plan, so read both before work starts. In England, national planning policy expects waste from construction to maximise reuse and recovery and minimise off-site disposal.

What to put in a SWMP

The revoked 2008 rules are still a sound template. Set out these details at the start of the job:

  • the client, the principal contractor and whoever wrote the plan
  • the site address, a description of the work and its estimated cost
  • design and method decisions made to cut waste
  • each waste type expected, with an estimated quantity
  • what will happen to each type: reuse, recycling, other recovery or disposal
  • a statement that waste will be handled under the duty of care

How to write the plan, step by step

1. List and code the waste

Go through the job stage by stage: strip out, demolition, groundworks, build and fit out. Give each waste its List of Waste code (often called an EWC code), because you need it for the transfer note. Soil and stones that are not hazardous are 17 05 04, for example, and non-hazardous gypsum such as plasterboard is 17 08 02.

Flag anything that may be hazardous early. If soil may be contaminated, get it tested before you book a muck away. See where to tip contaminated soil and licensed routes for asbestos.

2. Estimate the quantities

Put a figure in tonnes or cubic metres against each waste. Use drawings, excavation volumes and records from similar jobs. These figures tell you how many loads to plan for and give you something to compare against at the end.

3. Work down the waste hierarchy

The order is prevention, preparing for reuse, recycling, other recovery, then disposal. Applying it is a legal duty when waste is transferred, and in England and Wales the transfer note must confirm you have done so. Scotland and Northern Ireland have equivalent duties.

In the plan, record how you will order accurately, reuse material and keep waste streams apart. Keep plasterboard out of mixed loads, because gypsum must not go into a landfill cell that takes biodegradable waste.

4. Plan any reuse on site legally

Waste soil or crushed hardcore cannot simply be spread or buried on land. Depositing waste on land without an environmental permit or a registered exemption is a criminal offence in every UK nation. Landowners who allow it can be liable too.

In England, the U1 exemption allows limited use of suitable, uncontaminated waste in construction. It must be registered before any waste arrives. Limits include 1,000 tonnes of soil and stones or 5,000 tonnes of brick, concrete and similar waste over 3 years. It does not cover landscaping, land raising or reclamation as a job in its own right. New exemption rules are due from January 2027, subject to parliamentary approval, so check the current U1 guidance first.

Exemptions differ in Scotland, Wales and Northern Ireland. Ask SEPA, Natural Resources Wales or NIEA before you plan any reuse there.

5. Name the carrier and the destination for each waste

Record who will carry each waste, their registration number and the receiving site. Check the carrier on the public register for the nation they are registered in, and confirm the site’s permit covers that waste. Carrying your own construction or demolition waste still needs upper tier registration in England, Wales and Northern Ireland, and the waste carrier guide covers the detail. To find a receiving site, search by postcode on Tip Directory.

6. Record every load and review the plan

Each time waste leaves site, log the date, waste type, quantity, carrier and destination. Review the plan regularly, and at the end of the job compare estimated quantities with actual ones and explain any differences.

Paperwork to keep with the plan

A SWMP does not replace your legal waste records.

Record Applies to Keep for
Waste transfer note Non-hazardous waste, all four nations At least 2 years
Hazardous waste consignment note England, Wales and Northern Ireland 3 years for producers and holders
Special waste consignment note Scotland 3 years for producers and holders

In Wales, premises producing or storing more than 500kg of hazardous waste a year must also register with Natural Resources Wales. For the wider rules, see the duty of care guide.

Changes that affect your plan

Digital waste tracking: Permitted receiving sites in England and Wales have had to report every load digitally since 1 October 2026. Defra’s timetable has Scotland and Northern Ireland following in January 2027, and waste collectors from a planned date of October 2027. Transfer notes and consignment notes continue until further notice.

Carrier permits in England: Under regulations made in 2026, waste carrier, broker and dealer registration begins moving into the environmental permitting system on 22 July 2027. Wales keeps its current registration system. Upper tier carriers move across when their registration comes up for renewal, so check the carrier’s status on long jobs.

Sources